If you are planning a new single-family home in the City of Orlando, the permit process is more than filling out one application and waiting for an approval. The City will review where the house sits on the lot, how the proposed development fits the zoning rules, whether the permit package contains the required documents, and whether the submitted construction information complies with the requirements each reviewer administers. After the permit is issued, inspections continue that regulatory process during construction.
You do not need to become a zoning specialist or plans examiner to follow what is happening. You do need a clear mental model of the sequence, the documents, and the people involved. This guide explains that process for a new single-family home inside Orlando city limits and points you to the City’s live resources for details that can change.
First, make sure the property is actually in the City of Orlando
An Orlando mailing address does not necessarily mean the property is inside Orlando city limits. A property may have “Orlando” in the postal address but be in unincorporated Orange County or another municipality. That distinction matters because the governing city or county controls the zoning rules, permit office, application system, review routing, and local procedures.
Before relying on this guide, verify the jurisdiction. Practical ways to do that include:
- Use the City of Orlando’s Check Your Address tool.
- Search the parcel on the Orange County Property Appraiser website and look for the municipality or jurisdiction shown for the property.
- If the online records are unclear, contact City Planning or Permitting Services with the property address or parcel ID and ask whether the parcel is inside City limits.
Why this matters: starting with the wrong jurisdiction can send you to the wrong zoning rules, forms, portal, or permit checklist before the project has even reached plan review.
Learn a few terms before you start
Permitting becomes much easier to understand once a few common terms are clear.
- Jurisdiction means the government with legal authority over the property for the issue being discussed. For this guide, the key question is whether the property is governed by the City of Orlando for zoning and building permitting.
- Zoning is the City’s land-development rule system. It controls what types of development are allowed and how buildings and site improvements may be arranged on a property.
- A setback is a required distance between a building or site feature and a property line or other regulated boundary.
- An overlay is an additional set of rules that applies to a mapped area on top of the underlying zoning. A Planned Development, often shortened to PD, can also contain development-specific standards that differ from a generic zoning district.
- Impervious surface means a surface that sheds rather than absorbs rainfall, such as many roofs, driveways, and paved areas. The City uses Impervious Surface Ratio, or ISR, as one way of measuring how much of a lot is covered by impervious surfaces.
- A survey documents property information within the surveyor’s professional scope. A site plan uses property information to show where the proposed house and site improvements will be located. They are related documents, but they do not serve the same purpose.
These definitions are intentionally simple. A specific property can involve additional rules, exceptions, overlays, easements, floodplain conditions, or other requirements that need project-specific verification.
Start with zoning before you prepare the permit package
The City of Orlando’s Residential Development Standards Guide starts with the property’s zoning category and the development standards that apply to the proposed housing type. That is the right order for a homeowner to think about the project too.
A house can be well designed and still need revision if the site arrangement does not fit the rules for the property. Depending on the parcel, zoning and related development standards can affect setbacks, building height, lot coverage, impervious surface, parking and driveways, sidewalks, trees and landscaping, floodplain issues, and other site conditions.
Do not assume a setback or lot-coverage number from another Orlando project applies to yours. The applicable standards can depend on the zoning district, overlays, whether the property is in a Planned Development, whether the lot is legally nonconforming, and other property-specific conditions. The City’s current zoning tools and code—not a generic online table—should control the project-specific answer.
A useful early sequence is:
- Confirm the property is inside City limits.
- Identify the zoning district or development framework that applies.
- Review the standards that affect a new single-family home on that property.
- Identify overlays, PD requirements, floodplain conditions, tree requirements, or other special issues that may change the site plan.
- Develop the house and site plan with those constraints in mind before the permit set is treated as finished.
Why this matters: zoning problems are easier to address while the home and site plan can still change. Discovering a basic site conflict after the construction documents are highly developed can create avoidable redesign and coordination work.
Understand who does what
A permit package is usually the product of several people, and their responsibilities are not interchangeable.
- Homeowner — provides owner and property information, makes project decisions, signs required owner documents, hires the project team, and stays aware of unresolved owner-side requirements.
- Residential design provider or architect, where applicable — develops the home design and construction documents within the agreed scope and responds to design-related review comments within that scope.
- Surveyor — provides survey information within the surveyor’s professional scope. That information can become the basis for site planning and other permit documents.
- Structural engineer and other consultants — prepare specialized designs, calculations, signed or sealed documents, and responses for matters within their professional scopes.
- Builder or permit applicant — on a typical contractor-built project, the contractor commonly submits or leads the building-permit process and coordinates construction-side permit administration. The actual applicant and authorized representatives depend on the project and agreements.
- City Planning and zoning staff — administer the City’s land-development and zoning requirements.
- Permitting staff and plans examiners — administer the permit application and review the portions of the submitted documents that fall within their assigned responsibilities.
- Inspectors — inspect permitted construction at required stages after the permit is issued.
The City’s current residential permitting checklist uses broad architect/engineer signature language for plans. Florida law also contains an exemption from architect licensure for certain one-family and two-family residential work. Those two facts should not be simplified into the claim that every drawing in an Orlando single-family permit package must be prepared by an architect. A permit package can include building-design drawings, structural engineering, surveys, energy documentation, and other items produced by different people. Confirm the City’s current submission and signature requirements for the actual project, and make sure each specialized document is prepared by the professional responsible for that work.
Know what generally goes into the permit package
The construction drawing set is a major part of the submission, but it is not necessarily the whole permit package. The City’s current Residential Permitting Requirements page identifies a residential building permit and, when applicable, separate trade permits for work such as electrical, plumbing, or gas systems.
Depending on the project, the submission may include categories such as:
- permit application and owner or contractor information;
- construction plans;
- legal description and property information;
- survey and site-plan information;
- structural drawings or calculations;
- energy documentation;
- grading, drainage, erosion-control, or other site-engineering information; and
- other forms, approvals, or supporting documents triggered by the property or project.
Not every project requires every item, and some properties create additional requirements. The City’s live Residential Permitting Requirements and Permitting Forms & Documents pages are better sources for the current project checklist than a static list copied into an article.
It is especially useful to understand that a survey, site plan, and grading or drainage plan answer different questions. The survey establishes property information within the surveyor’s scope. The site plan shows how the proposed home and improvements sit on the property. Grading and drainage information explains how elevations and water movement are addressed when that information is required. For some new-home projects, site engineering can be a substantial part of the permit package rather than a small attachment added at the end.
ProjectDox is the City’s digital plan-review system
ProjectDox is the City of Orlando’s electronic system for uploading plans and supporting documents, receiving review comments, submitting corrected files, and receiving approved stamped plans. If you have never used a digital permit-review system, think of ProjectDox as the shared online workspace where the official review files and review cycles are managed.
The City’s current process can be understood in seven broad steps:
- Submit the permit application. The City processes the application and creates the permit record.
- Receive access to ProjectDox. The person designated as the digital applicant receives the invitation and manages the electronic upload tasks.
- Prepare and upload the files. The City publishes file-naming, drawing-file, and digital-signature requirements that should be followed before upload.
- Complete prescreening. Prescreening is an initial file/completeness check. It helps determine whether the submission is ready to be routed for substantive plan review.
- Go through plan review. The applicable City reviewers examine the portions of the project within their responsibilities.
- Respond to comments and resubmit when necessary. A resubmittal is the corrected or revised information sent back for another review cycle.
- Complete approval and permit issuance. After the required reviews and administrative items are satisfied, remaining fees and contractor information are resolved and the approved permit documents become available.
The exact screen names and file rules can change, so use the City’s current Submit Construction Project Plans and Digital Plans Strategy pages when you are preparing an actual upload.
What happens when reviewers request changes
Plan-review comments are a normal part of permitting. A comment does not mean the house is badly designed. A reviewer may identify missing information, an inconsistency, a code or zoning issue, an unclear detail, a document-format problem, or another item that needs correction or clarification.
The important homeowner question is: who is responsible for the response?
A design comment should generally return to the design professional responsible for that information. A structural comment belongs with the structural engineer. A survey or boundary-information issue belongs with the appropriate survey professional. Other consultant comments should go to the person responsible for that work. The permit applicant commonly coordinates the overall resubmittal process on a contractor-led permit.
Corrections should be coordinated rather than patched independently. A change to the site plan may affect another drawing. A structural response may require a design drawing to be updated. A revised opening or roof condition can affect more than one sheet or consultant document.
The City’s current system allows revised files and responses to move through additional review cycles until the applicable reviewers are satisfied. A separate Alto66 Knowledge Base resource is planned for the deeper question of how permit-review revisions should be organized and resolved.
Pay attention to the code edition near the actual submission date
At the time this guide was verified, the City of Orlando lists the Florida Building Code, 8th Edition (2023), among the codes currently used for permitting. The Florida Building Commission is also working through the 9th Edition (2026), which is scheduled to become effective December 31, 2026.
If your project will be submitted near a code transition, do not assume that the edition in effect when design started will automatically be the edition used when the permit application is reviewed. Check the City’s Applicable Codes for Permitting page when the permit package is actually being prepared for submission.
Permit issued does not mean the process is finished
Once the required reviews and administrative conditions are satisfied, the City can issue the permit and make the approved plans and related permit documents available. That is an important milestone: construction can move forward under the issued permit and applicable requirements. It is not the end of the City’s involvement.
One document homeowners may encounter around this stage is the Notice of Commencement. A Notice of Commencement is a recorded document connected to Florida construction-lien law. The City provides instructions for submitting a recorded Notice of Commencement when applicable, and Florida law establishes timing requirements tied to inspections for qualifying projects. Because lien-law requirements can have legal consequences, follow the current City and statutory instructions and seek project-specific legal or title advice when needed rather than treating a short summary as legal guidance.
Keep the approved plans and revisions organized. The City identifies approved plans, the issued permit or inspection sheet, engineering documents, and other applicable records as jobsite documents that may be needed during inspections.
Inspections happen during construction
Plan review and inspection are different activities. Plan review happens primarily before permit issuance and evaluates the submitted documents. An inspection happens after work has been performed and allows the City to examine the permitted construction at required stages.
The City states that issued permits require inspections, but the exact inspection sequence depends on the work. A new home will involve inspections at multiple stages and disciplines before the permit can reach final status. The contractor commonly coordinates inspection scheduling and construction readiness, but homeowners should still understand that failed, missed, or incomplete inspections can affect project progress.
When the required inspections and closeout items have been completed, the permit can reach final status. Depending on the project and City process, a Certificate of Occupancy or Certificate of Completion may also be part of the final documentation. In plain language, “permit issued” means the project has been authorized to proceed under the permit; “permit final” means the required inspection and closeout process has been completed.
Questions to answer before the permit is submitted
Before a new single-family home enters City review, the project team should be able to answer most of these questions:
- Is the property definitely inside City of Orlando limits?
- What zoning district, PD, overlay, or other development framework applies?
- Which setbacks, site-development standards, floodplain issues, tree requirements, or other property-specific rules materially affect the design?
- Is the survey current and appropriate for the decisions and permit documents being prepared?
- Does the site plan clearly show how the proposed house and site improvements fit the property?
- Which drawings, calculations, forms, energy documents, site-engineering documents, and consultant materials are required for this project?
- Who is the permit applicant and who will act as the digital applicant in ProjectDox?
- Who is responsible for responding to design, structural, survey, site, energy, or other review comments?
- Are the City’s current file-naming, digital-signature, and upload requirements understood before ProjectDox submission?
- Which code edition and City requirements are expected to apply at the actual submission date?
- Are any Notice of Commencement, contractor, owner-builder, utility, fire-sprinkler, community, or other project-specific requirements still unresolved?
- Who will track review status, resubmittals, permit issuance, inspections, and final closeout?
If an answer is still unknown, record it as an open item. Permitting becomes harder to manage when an unresolved requirement is mistaken for someone else’s responsibility.
The main idea
For a new single-family home in the City of Orlando, the useful sequence is not “draw the house, submit the plans, get a permit.” The real process begins by confirming that the property is actually inside City limits and understanding the zoning and site rules that shape what can be proposed. The project team then assembles the construction, property, engineering, energy, and other supporting information required for the permit package. ProjectDox manages the City’s digital review cycles. After permit issuance, inspections and final closeout continue until the permitted work is complete from the City’s perspective.
You do not need to memorize every City form or inspection code. You do need to know which questions belong to zoning, which documents belong in the permit package, who is responsible for each part of the response, and where to find the City’s current instructions when the project reaches that step.
Official Resources
- City of Orlando — Check Your Address
- City of Orlando — Residential Development Standards Guide
- City of Orlando — Residential Permitting Requirements
- City of Orlando — Submit Construction Project Plans
- City of Orlando — Digital Plans Strategy
- City of Orlando — Permitting Forms & Documents
- City of Orlando — Applicable Codes for Permitting
- City of Orlando — Schedule or Cancel an Inspection
- City of Orlando — File a Recorded Notice of Commencement
Sources & References
- City of Orlando — Check Your Address
- City of Orlando — Residential Development Standards Guide
- City of Orlando — Residential Permitting Requirements
- City of Orlando — Submit Construction Project Plans
- City of Orlando — Digital Plans Strategy
- City of Orlando — Get a Permit
- City of Orlando — Schedule or Cancel an Inspection
- City of Orlando — Permitting Forms & Documents
- City of Orlando — Applicable Codes for Permitting
- Florida Legislature — Florida Statutes §481.229, exemptions from architecture licensure
- Florida Legislature — Florida Statutes §713.135, Notice of Commencement and permit-related requirements
- Florida Building Commission — Current Florida Building Code resources
- Florida Building Commission — 9th Edition (2026) Code Development